Schedule work items in your plan according to releases

このページでは、Jira Cloud Premium と Enterprise の一部としてのみ利用できる高度な計画機能について説明します。

Along with scheduling work items by sprints or set dates, you can schedule work items based on the release to which it’s assigned.

  1. Next to your plan’s name in the sidebar, select More actions (•••), then Plan settings.

  2. In the Scheduling tab under the Inferred dates section, choose which dates you’d like your plan to auto-populate when work items don’t have start and end dates. Choose from:

    1. なし

    2. スプリントの日付

      1. For work items that are part of a team-managed project, sprints must be enabled in that project. Find out how to enable sprints in team-managed projects.

    3. リリース日

Once enabled, you can schedule work items according to the release dates the work items are assigned to a release, but have no start or end date. From here, you can then manually adjust an work item’s dates without changing its release assignment. However, if you move a work item beyond the release date, your release will fall off-track and the icon will turn red.

In order to use this setting, releases in your plan need to be scheduled using Fixed dates. If your releases uses As soon as possible, After all work items are completed, or Relative to a previous release as a start or end date, the schedule bar fades out indicating that it can’t be determined.

[開始日] フィールドと [期限] フィールドの横には、以下に示すように R のバッジが表示されます。

Advanced Roadmaps for Jira Software Cloud でリリースに基づいてスケジュールする